Gannt Chart

Below is a Gantt chart, created to organise more efficiently what had to be completed in the set time frame. In red are the estimated completion times of each aspect and in grey is the actual time each section took to complete.


Completing the modelling took a week longer than expected which pushed other aspects behind schedule. However we believe that the extra time taken to complete the models was important in getting all models to look the best they could.

The animation stage also got pushed behind schedule due to the unexpected complexity of how some of the mechanisms moved. More time could have been spent on getting each mechanism to animate better but an extra week was the most the group could afford to allocate otherwise there would not have been enough time to create a professional looking video ready for the presentation.